Rapidus fails to build working SRAM on 2nm node, risking 2027 output
Japanese chipmaker Rapidus has reportedly missed a key summer milestone to show working SRAM on its 2nm node, threatening plans to start mass production by 2027.
Japanese government-backed chip venture Rapidus is running into serious technical hurdles on its 2-nanometer manufacturing process. The company missed a critical target to show working static random-access memory cells by summer 2026. Cleanroom contamination has also created operational issues at its manufacturing facility in Hokkaido.
Missing a vital memory milestone
Rapidus first began making test structures with 2nm-class Gate-All-AroundGate-All-AroundAn advanced transistor design where the control gate completely wraps around thin silicon channels. Open in glossary transistors in July 2025. Chief executive Atsuyoshi Koike later stated that those prototype transistors showed the expected electrical traits. However, moving from isolated transistors to working circuits is much harder.
Memory cells known as SRAMSRAMA type of fast on-chip memory that holds data as long as power is supplied. Open in glossary serve as internal cache memory in processors. Fabricating these memory blocks requires connecting multiple transistors alongside complex peripheral wiring and control logic. Foundry operators use these dense memory arrays as testbeds to uncover process defects, variations in transistor performance, and yield issues. Rapidus has not demonstrated working memory cells, leaving its yield at zero percent for this critical step.
Slipping timelines and steep hurdles
The technical setback puts the startup under tight deadlines. A chip foundry must show working memory cells, scale them into large arrays, achieve solid yields, qualify its production lines, and complete risk production about one year before commercial output begins.
Rapidus previously aimed to mass-produce chips in 2027. While it denies formal delays, company representatives told the Japan Times that production is targeted for the second half of fiscal 2027, which runs until March 31, 2028.
Building 2nm chips using extreme ultraviolet lithography remains one of the hardest tasks in the semiconductor industry. To date, only established giants like TSMC, Intel, and Samsung have entered volume manufacturing with Gate-All-Around hardware. Founded in 2022 and relying on technology developed by IBM, Rapidus faces the steep task of reproducing these complex chemical etching and patterning steps in an entirely new facility.
How does this story land?
One tap per reader.
Quick poll
Can Rapidus start volume 2nm chip production before April 2028?
One tap. No sign-up.
Ask this story
Still have a question?
Answers use only what is in this story. They are written by AI and can be wrong.